Cimbra® Architecture & construction — Madrid
ES
Prado School

Project 07 · School · 12 classrooms

Prado School

Location
Getafe
Client
Town council
Floor area
3,400 m²
Build time
13 months
Handover
2023

A nursery and primary school with green roofs the children can see from their classrooms.

We built the school next to the old one while it stayed open. The work was phased so access was never cut, and the noisy trades were concentrated in July and August.

The exposed-concrete stairs double as seating: on rainy breaks the lobby becomes a small theatre.

Main stair under the rooflight.
Main stair under the rooflight.
Lobby seating steps.
Lobby seating steps.
Stair down to the playground.
Stair down to the playground.

Location

Getafe

40.3057° N · 3.7329° W

Work
Next project Lamas Building →